Furnish & install 13.8kV, 480V, 120/208V distribution equipment and feeders & circuitry. Furnish & install UPS, fiber optic, direct transfer trip and automatic control systems and motor work.
Rehabilitation of all electrical and mechanical ventilation equipment. This project is the total replacement of a fully redundant electrical and mechanical system for the ventilation of the Holland Tunnel. Equipment being replaced is medium voltage switchgear, 480V switchgear and motor control centers. This equipment resides in four buildings, two New York, two in New Jersey. Equipment removals and replacements must be staged perfectly so that there is no interruption to tunnel service. |