|
Power Construction |
|
|
|
|
|
High Voltage
|
|
345kV Oil Filled Cable - East River Promenade |
|
Owner: |
Consolidated
Edison |
Location: |
401 East 34th Street (East
River Promenade)
New York, NY |
Client: |
Pirelli |
Value: |
$3,750,000 |
|
When 345,000 volt Con Edison cables required repair and replacement, E-J Electric Installation received the call from Pirelli, a leading international manufacturer of high voltage cable. They needed a contractor who had the ability to provide experienced electricians and the corporate agility that such a complex project demanded. The project called for using liquid nitrogen to freeze both ends of a 10" pipe filled with insulating oil, cutting out pipe sections replacing and splicing the cable. With the new 345kV cable in place, testing was performed and the cable returned to service. Delays were "not an option". |
Astoria
Energy 500MW Power Plant |
|
Owner: |
Astoria Energy
LLC |
Location: |
17-10 Steinway Street
Astoria, Queens |
Client: |
Shaw Stone & Webster |
Value: |
$51,000,000 |
|
A new 500 megawatt highly efficient electric generating facility using state of the art combined-cycle, technology and air pollution control systems. The major equipment includes combustion turbines, heat recovery steam generators, air pollution controls, and steam turbines. The facility uses air cooled condensers for the cooling system to significantly minimize water consumption. Natural gas is the primary source of fuel with low sulfur distillate fuel oil serving as a backup fuel for up to 720 hours annually. The Plant, located in the Queens load pocket, utilizes the transmission facilities at the existing Con Edison Astoria East Substation approximately one-half mile from the site to deliver clean, reliable electricity to New York City and the surrounding region. |
NYPA
500MW Poletti Power Plant |
|
Owner: |
New York Power
Authority |
Location: |
31-03 20 th Avenue
Astoria, Queens |
Client: |
Slattery Skanska |
Value: |
$82,000,000 |
|
The work at the NYPA500 project included the erection,
installation, and testing of (2) 200MVA GSU, (1) 234MVA
GSU, and (2) auxiliary transformers, in addition to the
installation and testing of (1) isolation transformer
and (3) excitation transformers.
Dead end and PT structures along with associated 138kV
switches were constructed to connect two of the three
GSU transformers to the overhead transmission lines fed
from the Astoria West substation. For design diversity,
a pothead structure along with the associated switches
was assembled to connect the third GSU to an underground
138kV feed which was also derived from the Astoria West
ring bus.
The low side of these GSU transformers utilized
a field welded 18kV Isophase bus to make the necessary
connections to the Combustion Turbine, and Steam Turbine
Generators as well as the auxiliary transformers. Power
from the auxiliary transformers was delivered to the
4160V switchgear via a 5kV cable bus. |
United Nations |
|
Owner: |
United Nations |
Location: |
42nd Street & 1st Avenue
New York, NY |
Client: |
United Nations |
Value: |
$370,000 |
|
Replaced Con Edison provided 2500kVA (13.8kV primary/ 120/208V secondary) transformer at United Nations headquarters. Provided 100 ton crane to hoist existing transformer out and hoist the new transformer into the sub-grade vault on United Nations property. The work was complicated by the location (off property on 1st Avenue) of the Con Edison truck delivering and taking away the transformers. Project involved disconnecting and re-connecting primary and secondary conductors as well as performing required "Hi-Potential" testing to Con Edison specifications. Surface grating was removed, modified and re-installed to accommodate the new installation. All work was performed "off-hours" and coordinated to avoid any conflict with ongoing United Nations operations. |
Terminal 4 – International
Arrivals Terminal JFK |
|
Owner: |
IAT LLC |
Location: |
JFK International Airport
Jamaica, Queens |
Client: |
AMEC Construction Management, Inc. |
Value: |
$34,500,000 |
|
The Terminal 4 project included a new 1.5 million square foot Terminal in JFK International Airport. E-J provided all power and lighting, lighting control system, deluge system, metering system and SCADA system. State-of-the-art architectural lighting was placed throughout the terminal. The three level glass walled central terminal building services 35 US and International carriers. There is an 850 foot long retail hall and the top level has a 500x400 departure lobby and 144 check-in positions. There is an 850 foot long retail hall. Special installations were performed for the International and US customs Departments. JFK's first Air Transit Station inside of a terminal is located between levels. |
American Airlines
Concourse C |
|
Owner: |
American Airlines |
Location: |
JFK International Airport
Jamaica, Queens |
Client: |
VRH/Torcon |
Value: |
$29,000,000 |
|
This project was part of the overall redevelopment of the American Airlines Terminal at JFK International Airport. E-J's scope was the primary service to all three substations on the site. In Concourse "C" E-J did all the distribution and entire building fit-out. Each substation was a "4pack" consisting of four lineups of S&C 5kV switch, transformers, network protector and network disconnect. At Concourse C the installation consisted of the collector bus and (2) 5000 Amp 480 Volt services as well as the installation of Taxi Way Lighting and Control. |
5 Times Square Office
Tower |
|
Owner: |
Boston Properties |
Location: |
5 Times Square
New York, NY |
Client: |
AMEC Construction Management, Inc. |
Value: |
$14,500,000 |
|
Tight sites for construction projects are not uncommon in New York. More often than not, project teams rise to the challenge. But when that site is landlocked by subway stations on three sides and a landmark theater on another, no room is left for Con Edison vaults below the sidewalks. The project team decided to put the vaults on the third floor of the new, $150 million, 38-story, 575-foot-high, 1.1 million square foot building.
E-J Electric’s team built a complete Con Edison Spot Network within the vaults. This network consists of four 4100-480/277Volt power transformers (with expansion capabilities to six), network protectors and collector bus. E-J ran 5kV power conductors, within concrete-encased five-inch rigid metal conduits that sweep up from behind street level to the third floor.
To deliver base building power E-J installed a lineup of four, 6000Amp service switchgear arrays, feeding four duct risers (one for every nine floors), with tap-offs to transformers. To compensate for the voltage drop experienced at higher floor levels, the bus duct runs are rated at both 4000A and 5000A.
A 1500 watt- rated standby diesel generator provides power for emergency lighting circuits and other vital loads, if utility-supplied power to the building is ever lost.
Combining creativity with technology, a unique façade lighting installation provides dramatic visual identification to this Times Square office tower. E-J Electric also installed an UL-listed lighting protection system for the office tower. |
Rockefeller Center
Chiller Upgrades |
|
Owner: |
Rockefeller Center
Management Group |
Location: |
30 Rockefeller Plaza, Building
1
New York, NY |
Client: |
PhilipsRockefeller Center
Management Group |
Value: |
$14,000,000 |
|
On this ten year, $14 million, upgrade of Rockefeller Center 's electrical
distribution, we shared a joint engineering office with the consulting engineers
and Rockefeller Center Management. All parties worked together to reach the
best design and price. E-J's input started at the outset, when a design was
just a concept, and continued through planning scheduling, purchasing and
construction.
A typical example of the advantages E-J provided through trade management
at Rockefeller Center was our prepurchasing of the 15kV equipment to keep
the job on schedule, procure the correct options for this specialized equipment
and obtain the best pricing.
We worked with the consulting engineer to produce specifications. Requests
for quotation were sent out and analyzed when returned. E-J then had meetings
with all vendors to review in detail their quotations and requested final
proposal focusing on specific technical details, price and schedule. The
result was a manufacturer who met all the technical requirements, construction
schedule and budgets of the Center.
To cut two months off the construction schedule, E-J arranged for the consulting
engineer, owner and our project manager to fly to the factory in Iowa to
sign off on shop drawings. This was critical in making the construction schedule
meet tenant requirements. |
World Trade Center - Standby Power |
|
Owner: |
Port Authority
of New York & New Jersey |
Location: |
World Trade Center Complex
New York, NY |
Client: |
VRH Construction |
Value: |
$7,100,000 |
|
Project consisted of rigging and setting of (4) 2000kW Caterpillar generator sets on the roof of Building
#5. The generators were installed in a new penthouse
along with paralleling switchgear, feeder breakers, 3000kW load bank and house load substation. (4) 15kV feeder
risers were run down Building #5 to the complex basement.
One riser was run up to the 108th floor of each of the
Twin Towers . The risers consisted of 5" rigid conduit
with armored 4/0 15kV cable. The other two risers fed
cooling water substations. The project also included
installation of two tenant emergency substations with
connection to tenant transfer switches. |
Throgs Neck Bridge – Rehabilitation of Electrical Systems |
|
Owner: |
MTA Bridges & Tunnel
Authority |
Location: |
Throgs Neck Bridge
Bronx/Queens,
NY |
Client: |
MTA |
Value: |
$6,100,000 |
|
Completion of the entire electrical system at the Throgs Neck Bridge. The bridge was operated under temporary generator power for 9 months. The 5kV Substation furnished all power to the Throgs Neck Bridge, Operational Building, Toll Complex and Maintenance Facility. Safety requirements included boat patrol during working hours. |
Visy Paper |
|
Owner: |
Visy Paper |
Location: |
44-35 Victory Blvd.
Staten
Island, NY |
Client: |
Visy Paper |
Value: |
$4,200,000 |
|
An 850 ton per day recycled paper mill, Visy Paper Project
is designed for truck and barge delivered waste paper
from New York City. The Process Building including stock
preparation, paper machine and reel storage area is 1100
feet long, 80 feet wide and 80 feet high. The project
included power (5kV) from substation to 5kV distribution
in plant including all 5kV motors, Six unit substations
5kV/480V, two unit substations 5kV/575V, temporary power
system, duct bank system, twelve motor control centers, six
variable frequency drive motor control centers, installation
of all loose shipped motors, installation of 9,000 feet
of cable tray, all power conduit and cable, fire protection,
All process area lighting and distribution, 5kV service,
five substations, MCC's, 5kV starters and VFD's (distribution
by cable tray). |
Montefiore
Cogeneration Plant |
|
Owner: |
Montefiore Medical
Center |
Location: |
111 E. 210th Street (Between
205th and Gunhill Road)
Bronx, NY |
Client: |
Keyspan Energy |
Value: |
$3,300,000 |
|
Cogeneration plant consisting of a 4.5MW 5kV Solar
Gas Turbine Generator Waste Heat Boiler. Installation
included one 5MW and two 2MW Generators, Cooling Tower
, and two Chillers. The project included 5kV paralleling
switchgear and associated unit substations and MCC's. |
Yonkers Raceway
Permanent/Temporary Service |
|
Owner: |
Yonkers Raceway
- Timothy J. Rooney |
Location: |
810 Central Park Avenue
Yonkers,
NY |
Client: |
Tishman Construction Corp |
Value: |
$7,000,000 |
|
This major renovation of Yonkers Raceway
includes
the Clubhouse, a new 98,000 sq. ft building, new lighting
and infrastructure upgrades for the entire site and parking
facilities. Project involves the installation of a primary 13kV medium voltage
electric service, generators, paralleling switchgear,
substations, utility primary switchgear, site ductbanks,
manholes and site lighting.
The 97.74 acres racetrack
renovation includes 7500 video lottery
terminals (VLT), restaurants, theater and parking for 5000
vehicles. The VLT's are housed in part of the existing
casino and new building. The entire facility is backed up
by emergency generators. Installation included replacing the four existing
#2/0 13kV service feeders with four new #350 kcmil 13kV feeders including manholes. E-J is installing owner
furnished double ended primary switchgear, three substations,
DC power panels, grounding and all electrical lighting/power
within the main switchgear rooms. The entire service,
switchgear and switchgear room will be installed to meet
all Con Edison requirements. In addition to this work
E-J is providing a 750kVA 5kV temporary service to facilitate
operation of the track while the permanent feeders are
renovated. The temporary feeders will also serve to energize
an existing substation in the clubhouse for use as the
project's overall temporary service. E-J is responsible
for providing detailed temporary switchgear and service
room engineered layouts. Under a separate contract E-J
will be installing four owner furnished 2000kW 13kV generators,
one prefabricated paralleling switchgear building, seven
medium voltage transfer switches, substations for the
new building, power feeders, control wiring and interfacing
with the new permanent service. The generators will be
remotely located in a dedicated yard. We will provide
new ductbanks and manholes to distribute power among
the entire facility. |
Con Edison Waterside
Generator Facility |
|
Owner: |
Con Edison |
Location: |
1st Avenue & 39th Street
New York, NY |
Client: |
Con Edison |
Value: |
$2,700,000 |
|
Electrical installation of Asea Brown Boveri Turbine
including all controls, LAN and 13.8kV Iso phase bus
duct and switchgear. |
Global Center - Emergency
Power |
|
Owner: |
Global Center |
Location: |
111 8th Avenue
New York, NY |
Client: |
Global Center |
Value: |
$2,600,000 |
|
E-J Electric
Installation Co., was the prime contractor for the installation
of (3) 2000kW generators on the rooftop of the old Port
Authority of New York & New Jersey Building. E-J subcontracted
the mechanical and steel installations and integrated the
new emergency power into the existing electrical distribution
system. |
American Museum
of Natural History - Vaults (Phase I) |
|
Owner: |
American Museum
of Natural History |
Location: |
Central Park West @ 79th Street
New York, NY |
Client: |
Morse Diesel International |
Value: |
$2,500,000 |
|
E-J's installation included six 13kV vaults and network compartments servicing new Hayden Planetarium and American Museum of Natural History Campus. We also installed four Con Edison transformers with associated switchgear and feeders. |
Rockefeller
University - Cogeneration |
|
Owner: |
Rockefeller University |
Location: |
1230 York Avenue
New York, NY |
Client: |
Rockefeller University |
Value: |
$1,200,000 |
|
Multiple medical laboratory installations including sensitive ground fault power, coldroom controls, darkroom and surgery lighting, and fire, security, and computer networking systems. Installation of outdoor substation including 1000kVA transformer to provide emergency backup for critical loads. |
Arthur Kill Staten
Island Landfill High Voltage Distribution |
|
Owner: |
NYC Dept. of Sanitation |
Location: |
Arthur Kill Staten Island Land
Fill
Staten Island, NY |
Client: |
Interstate/MJR Electrical Contracting |
Value: |
$300,000 |
|
Installed
5kV overhead distribution (3) dressed poles - installed
wire and terminated. |
1450 Broadway |
|
Owner: |
Lasalle Partners Management |
Location: |
1450 Broadway
New York, NY |
Client: |
Lasalle Partners Management |
Value: |
$150,000 |
|
Office Building where we replaced two 15kV riser cables |
Reliant Cable Replacement |
|
Owner: |
Reliant Energy |
Location: |
Astoria Power House
Astoria
, NY |
Client: |
Reliant Energy |
Value: |
$150,000 |
|
15kV 750
MCM Cable installed in 5" rigid conduit. Cable was
spliced into existing feeder at Reliant's power plant in
Astoria. |
NY/NJ Port Authority Bus Terminal |
|
Owner: |
Port Authority Bus Terminal |
Location: |
New York, NY |
Client: |
VRH Construction Corporation |
Value: |
$2,600,000 |
|
E-J Electric is a preferred contractor as a result of their workmanlike efforts and dependability. All work at the PABT has to be precisely coordinated with the facility so bus service and passenger comfort and safety is not impacted. E-J has been involved in a number of high profile projects beginning with the ADA Gate Modification Project. This two year facility-wide project included 106+ gates and has enabled the PABT to become ADA compliant. The Motor Stair Entrance Renovation on the main level was designed specifically to make passenger stairways safer and more efficient for all commuters departing and arriving through the installation of new lighting and the renovated fire alarms system. The renovation and new build-out of the tenant restrooms was designed to provide improved lavatory facilities for public access and transportation personnel. This project included lighting, power, HVAC, and control work. Our signature project has been the replacement chiller project. E-J'S medium voltage scope of work consisted of installing four new chillers and starters. The installation included 5kV feeders to the new 4th floor chiller plant. The 3rd floor plant was reconfigured which dictated a careful blending of new and old circuiting. Large additions to the base building fire alarm system, CCTV, and an extensive intricate control work was performed on the low voltage systems. |
|
|
|
|
|
|
|
|
|
|