E-J Electric Installation Co.

Power Construction

 

Utility Vaults

spacer

Vault & Primary Distribution of Atlas Park


Owner: ATCO Properties & Management Inc.
Location:    80th Street & Cooper Avenue
Glendale, NY
Client: Plaza Construction
Value: $4,750,000

E-J Electric was the prime contractor for the complete structural, mechanical and electrical installation for the thirteen acre site's main power distribution including Con Edison utility vaults.

The installation required routing 27kV Con Edison feeders underground to (4) 2000kVA transformers feeding network protectors bussed directly to 480 Volt switchgear.

The distribution across the site is a 480 Volt system via ductbanks and manholes. The longest feeds utilized (2) 5kV unit substations in a step-up step-down configuration.

American Airlines Concourse C


Owner: American Airlines
Location:    JFK International Airport
Jamaica, Queens
Client: VRH/Torcon
Value: $29,000,000

E-J performed the installation of all primary normal and emergency service at the American Airlines new terminal at JFK International Airport . Primary Service came in at 4160V. The project consisted of 3 normal power substations and 3 emergency power substations. Normal power substations consisted of 4 lineups each consisting of S&C 5kV load interuptor /ground switch, 4160/480V transformer, Network Protector and Network Disconnect. The 4 lineups were brought together via a collector bus which fed (2) 5000A Switchboards. Emergency Power substations consisted of 1 line up consisting of 5kV load interuptor/ground switch, 4160/480V transformer and distribution switchboard. Also installed was all primary feeder work. This consisted of ductbanks and feeder cable from utility manholes in the street to each substation. We also installed Aviation rated manholes. Feeder cables were 500 MCM flatstrap for normal power and 4/0 flatstrap for emergency power.

5 Times Square Office Tower


Owner: Boston Properties
Location:    5 Times Square
New York, NY
Client: AMEC Construction Management, Inc.
Value: $14,500,000

Tight sites for construction projects are not uncommon in New York. More often than not, project teams rise to the challenge. But when that site is landlocked by subway stations on three sides and a landmark theater on another, no room is left for Con Edison vaults below the sidewalks. The project team decided to put the vaults on the third floor of the new, $150 million, 38-story, 575-foot-high, 1.1 million square foot building.

E-J Electric’s team built a complete Con Edison Spot Network within the vaults. This network consists of four 4100-480/277Volt power transformers (with expansion capabilities to six), network protectors and collector bus. E-J ran 5kV power conductors, within concrete-encased five-inch rigid metal conduits that sweep up from behind street level to the third floor.

To deliver base building power E-J installed a lineup of four, 6000Amp service switchgear arrays, feeding four duct risers (one for every nine floors), with tap-offs to transformers. To compensate for the voltage drop experienced at higher floor levels, the bus duct runs are rated at both 4000A and 5000A.

A 1500 watt- rated standby diesel generator provides power for emergency lighting circuits and other vital loads, if utility-supplied power to the building is ever lost.

Combining creativity with technology, a unique façade lighting installation provides dramatic visual identification to this Times Square office tower. E-J Electric also installed an UL-listed lighting protection system for the office tower.

American Museum of Natural History - Vaults (Phase I)


Owner: American Museum of Natural History
Location:    Central Park West @ 79th Street
New York ,NY
Client: Morse Diesel International
Value: $2,500,000

E-J's installation included six 13kV vaults and network compartments servicing new Hayden Planetarium and American Museum of Natural History Campus. We also installed four Con Edison transformers with associated switchgear and feeders.

Brooklyn Army Terminal Vaults


Owner: NYC Development Corporation
Location:    140-58th Street
Brooklyn, NY
Client: Turner Construction Co.
Value: $1,900,000

Installation of (6) 27kV vaults and network compartments servicing Brooklyn Army Terminal including (3) 2500kVA transformers with associated collector bus, network protectors, switchgear and feeders, ventilation control and alarm systems.

Korean Air Cargo


Owner: Korean Airlines
Location:    Building 260, JFK International Airport
Jamaica, NY
Client: Turner Construction Co.
Value: $1,400,000

E-J's installation included dual 5kV building utility feeds, site lighting, communications and power feeds as well as feeds for airplane ground power units for the entire site including Cargo Building, future Cargo Building and surrounding airside work. The work also included ten manholes throughout the site.

7 World Trade Center Substation


Owner: Consolidated Edison/Silverstein Properties
Location:    7 WTC
New York, NY
Client: Tishman Construction
Value: $2,950,000

E-J prepared at 7 World Trade Center the space for the Con Ed utility substation including five 138kV transformers. The work consisted of providing temporary service of 4,000 amp for the initial and future phases of construction. E-J also installed nine miles of conduit for medium-voltage and high-voltage distribution duct banks and installed 8-ft by 8-ft horizontal ground plates with cad-welded conductors as well as ground rods, to provide complete building lightning protection and grounding system. All grounding was tested to exacting Con Edison "Fall of Potential" specifications.

Grasslands Substation


Owner: Consolidated Edison of New York Inc.
Location:    95 Grasslands Road
Valhalla, NY
Client: Consolidated Edison of New York Inc.
Value: $3,500,000

The Grasslands Substation project called on E-J Electric to provide the complete "above grade" electrical package. The work within this scope included the rigging and placement of switchgear, a complete 3000A/4500A bus duct system, installation and termination of all control and power cables, placement and wiring of all control room equipment, (2) 500kVA station power transformers, complete fire alarm system, complete public address/paging system and completion of two 138kV/13.8kV transformer bays which included welding of cable bus, installation and adjustment of circuit switchers and circuit interrupters and all 125VDC control devices.

The station was completed on an aggressive schedule, made challenging by one of the areas most severe winters. This was the first time that Consolidated Edison Co. contracted this complete scope of work.


E-J Electric Installation Co.     |     46-41 Vernon Boulevard     |     Long Island City, NY 11101     |     Phone: 718-786-9400     |     Fax: 718-937-9120     |     Email: ejelectric@ej1899.com