Major Projects |
|
|
|
|
|
Health Care & Laboratories
|
|
Bronx
Lebanon Hospital |
|
Owner: |
Bronx Lebanon Hospital |
Location: |
1650 Grand Concourse
Bronx,
NY |
Client: |
AMEC Construction Management, Inc. |
Value: |
$14,100,000 |
|
As Electrical
Trade Manager of this $120,000,000 new construction and renovation
project, the E-J team started involvement when drawings were
60% complete. They worked toward a GMP with engineers, architects,
and construction managers, developing cost savings of 2.5
million dollars to bring the project under budget for the
financially burdened hospital center.
Continuing responsibilities
included letting all contracts and monitoring the fulfillment
of minority goals for tradesmen, suppliers, and contractors. In the process E-J maintained
the quality of the end product. From design through construction,
E-J offered value engineering based on our extensive
installation experience. |
Interfaith
Medical Center |
|
Owner: |
Interfaith Hospital |
Location: |
480 Herkimer Street
Brooklyn,
NY |
Client: |
Turner Construction Co. |
Value: |
$9,500,000 |
|
New construction
and modernization of entire hospital (6 floors). This 3-year,
9 million dollar contract consisted of a new emergency
room, brought on line in phase one to keep hospital operative,
a new addition of an 85,600 square foot facility and the
renovation/modernization of an existing structure made
up of 154,000 square feet. The project included an extensive
Fire Alarm System, a Nurse Call System, a Medical Gas Alarm
System, a Pre-action System, a UPS System, a 1250kW Emergency
Generator, Low Voltage System and Specialty Radiology Systems
along with lighting and power systems. |
Memorial
Sloan Kettering Cancer Research Center |
|
Owner: |
Memorial Sloan
Kettering Cancer Center |
Location: |
415-418 East 68th Street
New
York, NY |
Client: |
Turner Construction Co. |
Value: |
$8,240,000 |
|
The new 238,800
square foot Memorial Sloan Kettering Cancer Research Center
took the place of an existing structure. This state of
the art research building provides the technology and space
to advance cancer research.
The Bottle Glass wash system is one of the specialty equipment systems we will
receive, assemble and wire along with many X-ray machines and the bedding
system. We also furnished and installed all Security conduit on the
floors and the telecommunications main conduit system that interconnects
Phase I & Phase II with the MDF Room. |
Montefiore Cogeneration |
|
Owner: |
Montefiore Medical
Center |
Location: |
111 E. 210th Street (Between
205th and Gunhill Road)
Bronx, NY |
Client: |
Keyspan Energy |
Value: |
$3,300,000 |
|
Cogeneration plant consisting of a 4.5MW 5kV solar gas turbine generator waste heat boiler. Installation included (1) 5MW and (2) 2MW generators, cooling tower, and two chillers. The project included 5kV paralleling switchgear and associated unit substations and MCC’s. |
DNA
Laboratory |
|
Owner: |
Bellevue Hospital |
Location: |
462 1st Avenue
New Yok, NY |
Client: |
Bovis Lend Lease LMB Inc. |
Value: |
$2,100,000 |
|
Project included
service feeder bus, fire pump, power, lighting and fire
alarm for new forensics DNA Lab at Bellevue hospital in
the Basement, 8th floor, 9th floor and Roof. |
Mt.
Sinai – Emergency Power Expansion |
|
Owner: |
Mt. Sinai Medical
Center |
Location: |
Annenberg Building
New York,
NY |
Client: |
Mt. Sinai Medical Center |
Value: |
$4,200,000 |
|
As a Prime Contractor on this project, our scope included all electrical and general construction work required to furnish and install two new 1500kW generators, complete with Zenith automatic synchronization switchgear, ten automatic transfer switches and a new 20,000-gallon fuel oil tank. This equipment was installed in a fully functional hospital and research facility without disruption of day to day operations. The power distribution from the generator consists of the installation of over 15,000 feet of 3 ½” conduit and 50,000 feet of cable from the third sub-basement generator room to the main service room on the 9th floor and a conduit system up to the 27th floor.
Due to space restrictions, the generators and 3,000 ampere transfer switch had to be disassembled and reassembled. The vertical risers required the use of a bosum’s chair for access into the available riser space. The project was completed in approximately 10 months from start to finish.
|
St.
Lukes Roosevelt Hospital |
|
Owner: |
St. Lukes Roosevelt
Hospital |
Location: |
1111 Amsterdam Avenue
New
York, NY |
Client: |
Bovis Lend Lease |
Value: |
$4,700,000 |
|
This renovation
of seven buildings that made up the South Block, included the
installation of systems such as fire alarm, nurse call,
paging, A/V and a high tech Conference Center. There were
also emergency and normal power upgrades and the complete
re-design of power and the fire alarm system to utilize
existing services and minimize hospital disruptions. The emergency room was fully renovated in phases to maintain the area's Critical Trauma Center. |
Rockefeller University - Cogeneration |
|
Owner: |
Rockefeller University |
Location: |
1230 York Avenue
New York ,NY |
Client: |
Rockefeller University |
Value: |
$1,200,000 |
|
Multiple medical laboratory installations including sensitive ground fault power, coldroom controls, darkroom and surgery lighting, and fire, security, and computer networking systems. Installation of outdoor substation including 1000kVA transformer to provide emergency backup for critical loads. |
New York Hospital
C.V. Starr Pavilion |
|
Owner: |
New York Hospital |
Location: |
1300 York Avenue
New York,
NY |
Client: |
Crow Construction |
Value: |
$15,000,000 |
|
Completed entire
new C.V. Starr Pavilion, incorporating electrical requirements
for latest medical systems. The Hospital is served through
an emergency power system that integrates a new 550V, 900kW,
diesel generator with three identical existing diesel generators,
to become part of an automatic paralleling scheme. The paralleling
of four on-site generators provides high reliability and
continuity of service. |
Beth Israel Medical
Center |
|
Owner: |
Beth Israel Medical
Center |
Location: |
330 East 17th Street
New York,
NY |
Client: |
Beth Israel |
Value: |
$400,000 |
|
Gillman Hall
chiller replacement, service replacement including interface
with Con-Edison, power for new roof chillers and multiple
projects over the last 25 years. |
Stamford Hospital 4th Floor Cardiology/Telemetry |
|
Owner: |
Stamford Health Systems |
Location: |
Shelborne Ave. @ West Broad Street
Stamford, CT |
Client: |
West Contracting Corporation |
Value: |
$300,000 |
|
Conversion of existing 5,000 sq. foot wing to a new 32 bed Cardiology and Telemetry special care wing. Work included furnishing and installing new architectural lighting systems, new power distribution, new nurse call, code blue and elapsed timer/clock systems. E-J worked closely with the General Contractor and design team to meet the stringent requirements of the owner for this high profile project. |
|
|
|
|
|
|
|
|
|
|