Astoria Energy 500MW Power Plant


Owner: Astoria Energy LLC
Location:    17-10 Steinway Street
Astoria, Queens
Client: Shaw Stone & Webster
Value: $51,000,000

A new 500 megawatt highly efficient electric generating facility using state of the art combined-cycle, technology and air pollution control systems. The major equipment includes combustion turbines, heat recovery steam generators, air pollution controls, and steam turbines. The facility uses air cooled condensers for the cooling system to significantly minimize water consumption. Natural gas is the primary source of fuel with low sulfur distillate fuel oil serving as a backup fuel for up to 720 hours annually. The Plant, located in the Queens load pocket, utilizes the transmission facilities at the existing Con Edison Astoria East Substation approximately one-half mile from the site to deliver clean, reliable electricity to New York City and the surrounding region.

Fresh Kills Methane Recovery Plant


Owner: DQE
Location:    100 Muldoon Avenue
Staten Island
Client: DQE
Value: $7,650,000

New Methane Recovery Plant at the Freshkills Landfill in Staten Island. The electrical installation included two new methane Krysol processing systems and the upgrade of the existing Solexol plant and remote flare stations. The installation consisted of a new 15kV service with associated unit substations, MCC's and instrumentation. There were eight methane powered generators connected to independently power the processing plant.

Visy Paper


Owner: Visy Paper
Location:    4435 Victory Blvd.
Staten Island, NY
Client: Visy Paper
Value: $4,200,000

An 850 ton per day recycled paper mill, Visy Paper Project is designed for truck and barge delivered waste paper from New York City. The Process Building including stock preparation, paper machine and reel storage area is 1100 feet long, 80 feet wide and 80 feet high. The project included power (5kV) from substation to 5kV distribution in plant including all 5kV motors, Six unit substations 5kV/480V, two unit substations 5kV/575V, temporary power system, duct bank system, twelve motor control centers, six variable frequency drive motor control centers, installation of all loose shipped motors, installation of 9,000 feet of cable tray, all power conduit and cable, fire protection, All process area lighting and distribution, 5kV service, five substations, MCC's, 5kV starters and VFD's (distribution by cable tray).